M
Mark Etheridge
Hello,
Each of my tasks have predessors (or all the tasks are linked) so that if I
change a task, the remaining tasks will automatically update.
The problem I have is that if one task gets moved out, the following task
start date will be the same as it's predecessor end date. I usually have to
manually go through each task to ensure the correct start dates. How can I
set it so that microsoft project will automatically push out the dependency
tasks to start the following day???
I hope this description makes sense?
Mark
Each of my tasks have predessors (or all the tasks are linked) so that if I
change a task, the remaining tasks will automatically update.
The problem I have is that if one task gets moved out, the following task
start date will be the same as it's predecessor end date. I usually have to
manually go through each task to ensure the correct start dates. How can I
set it so that microsoft project will automatically push out the dependency
tasks to start the following day???
I hope this description makes sense?
Mark