How Do I print a report with both tasks started and tasks remaining for a
resource. I cannot seem to do this in one report. I need it per resource
basis. Any help is welcome.
 
J

John

Theregoes said:
How Do I print a report with both tasks started and tasks remaining for a
resource. I cannot seem to do this in one report. I need it per resource
basis. Any help is welcome.

Theregoes,
Why not simply use the Resource Usage view with a filter for tasks that
have less than 100% Work Complete. You could also add an interactive
filter to isolate individual resources if desired. As I recall there is
a built-in Report (To Do List maybe) which provides similar information.

Hope this helps.
John