Hi Stretch,
Use the Project Date Value function. For example:
IIf([Baseline Finish]= ProjDateValue("NA"), "Has baseline", "No Baseline
Saved")
For additional information see fellow MVP Jack Dahlgren's blog page:
http://zo-d.com/blog/archives/programming/working-with-custom-field-formulas.html
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
Stretch said:
How do I test to see if a Baseline Start (or Finish) date exists?
I've tried testing for "NA" but was unsuccessful.
Thanks,
Stretch