Un-Split In-Progress Tasks

A

Alone

Does anyone know how to Un-Split In-Progress Tasks (or point me to someone
who has posted a macro to accomplish this work)?

TIA

Alone
 
J

JulieS

Hi Alone,

I assume you split the tasks through tracking and using the Tools > Tracking
Update Project, Reschedule uncompleted work to start after: command. If
you split the tasks in some other way, do let us know.

That will split tasks moving the incomplete portion of the task to the date
specified in the Update Project command.

You may manually "re-join" split tasks by dragging the split portion on the
right back into the left portion.

Another option if you have split many tasks by the Update Project command is
to use the Reschedule uncompleted work to start after command again, but
change the date to the last tracking you have applied.

I hope this helps. Let us know how you get along.

Julie
 
A

Alone

Thanks Julie,

I'll give it a try.

Alone

JulieS said:
Hi Alone,

I assume you split the tasks through tracking and using the Tools > Tracking
you split the tasks in some other way, do let us know.

That will split tasks moving the incomplete portion of the task to the date
specified in the Update Project command.

You may manually "re-join" split tasks by dragging the split portion on the
right back into the left portion.

Another option if you have split many tasks by the Update Project command is
to use the Reschedule uncompleted work to start after command again, but
change the date to the last tracking you have applied.

I hope this helps. Let us know how you get along.

Julie
 
A

Alone

Worked,

Thanks MUCHO.



JulieS said:
Hi Alone,

I assume you split the tasks through tracking and using the Tools > Tracking
you split the tasks in some other way, do let us know.

That will split tasks moving the incomplete portion of the task to the date
specified in the Update Project command.

You may manually "re-join" split tasks by dragging the split portion on the
right back into the left portion.

Another option if you have split many tasks by the Update Project command is
to use the Reschedule uncompleted work to start after command again, but
change the date to the last tracking you have applied.

I hope this helps. Let us know how you get along.

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top