rexepic said:
I work with a series of task on every project we do. I have a deadline
stored
for each project and can derive a duration for each task. I need to
chart
these task since each is a predecessor to the previous task so I can
arrive
at a start date for the project. Seems like it would be easy enough to
define
custom duration days 1-10 then back up from deadline to have a start
date on
the first task, but I have been unable to get custom fields to work
anything
like regular duration, start and finish. I need to see my custom
fields
plotted out on a gant chart! HELP
Hi rexepic,
I don't know what you tried but the following worked for me. I created
a series of tasks leaving duration at 1d? Add Duration1, Start1, Finish1
to the Entry table. In the *last task* I entered the deadline date in
the Finish1 field. I entered the estimated duration for the task in the
Duration1 field. In the Start1 field I added a formula:
ProjDateSub([Finish1],[Duration1],"standard")
This will calculate the Start1 date based upon the Finish1 date minus
Duration1. Once Start1 is calculated for the last task, copy and paste
the Start1 from that task to the Finish1 of the predecessor task. (This
essentially creates a Finish - To- Start schedule). You can certainly
type in the finish1 dates, I just find copying and pasting is faster.
Follow the process upwards in your project to show Start1 for the first
task.
To draw the Gantt bars, create a new bar style (Format > Bar Styles) and
draw the lines from Start1 to Finish1.
(As an aside, you can also have Project help determine the start date of
a project after you have loaded tasks, set durations, and links, by
switching the method project usually uses to calculate finish dates of
projects. Go to Project > Project Information and choose schedule from:
Project Finish Date. Enter your deadline date into the finish date,
click OK and project will calculate the start date. Go back to Project
Project Information, take note of the calculated Project Start date,
set your scheduling back to Project Start date and enter in the start
date -- I'd pad the start date a bit for good measure.)
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project