J
JM Cox
I am using project priorities to allocate limited
resources. I would like Project to allocate resources by
priority until each person's time is consumed. I want a
visual indication of which projects require overallocated
resources.
Alternatively, in the Resource Graph view, I would like to
see a stacked bar graph that shows the projects in
priority order.
Is there a way to do either of these two things?
Thanks,
jmc
resources. I would like Project to allocate resources by
priority until each person's time is consumed. I want a
visual indication of which projects require overallocated
resources.
Alternatively, in the Resource Graph view, I would like to
see a stacked bar graph that shows the projects in
priority order.
Is there a way to do either of these two things?
Thanks,
jmc