A
andylv
I have a couple of Gantt charts that are about 200 tasks long that I use to
manage my group's workload. Most of the tasks have multiple resources with
each resource assigned a certain percentage of time available.
I want to use these Gantt charts to forecast personnel requirements for my
budget for 2006.
We have projects that have 100%, 75%, 50%, and 25% probability. What I’d
like to be able to do is have the projects that have a 25% probability show
up as 25% resource requirement; another way to put is four 25% probability
projects would equal one 100% probability project in my resource graph.
How can I do this w/o adjusting each resource’s % of time assigned?
TIA,
Andy
manage my group's workload. Most of the tasks have multiple resources with
each resource assigned a certain percentage of time available.
I want to use these Gantt charts to forecast personnel requirements for my
budget for 2006.
We have projects that have 100%, 75%, 50%, and 25% probability. What I’d
like to be able to do is have the projects that have a 25% probability show
up as 25% resource requirement; another way to put is four 25% probability
projects would equal one 100% probability project in my resource graph.
How can I do this w/o adjusting each resource’s % of time assigned?
TIA,
Andy