Hi Jie,
I only get that checkbox when assigning a task calendar to a task (in fact I
only see it in Task Information, Advanced)
There its meaning is as follows:
When you assign to a task both a resource and a task calendar, Project will
schedule the task when both the task calendar and the resource calendar show
working time.
When however this box is checked the task will be scheduled based on the
task calendar only.
For instance, Resource Calendar is normal 5/7, Task Calendar is 7/7
When the box is checked a 3 day task starting on Fr morning ends on Su night
When not, it ends on Tue night
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Jie said:
Friends,
When I was setting the calender of my project to a new calender, there is
an checkbox. The content of this checkbox is "Scheduling ignores resource
calenders" . What if I check it?