R
Rob Schneider
Folks,
Having a bit of a mystery here. I have long experience with using
subproject files, and have never seen this. I'm hoping someone can help.
I have a project file, created by others, which a Project Start date of
Feb 20. Per the Project Summary Task Bar, Start is 15 Feb (where the
actual first start of the earliest task is) and Finish is 27 Mar 2007
(which is when the last task finishes). This looks all ok.
When we insert this MPP file as a subproject into another empty file
(using the same standard calendar), the Project Summary Task finish date
remains the same (27 March 2007), but mysteriously the Project Summary
start date changes to May 3. Further, non of the tasks in the
subproject file shift right. They are shown to to the left of the start
of the Project Summary bar.
Clearly the Project Summary bar when inserted is wrong. But I can't
figure out what is wrong and why it recomputes this.
Thinking this a problem with Project 2003 SP2, I tried with Project 2002
SP-1, but get same result.
What causes the Project Summary Task bar to be wrong when inserted into
another file?
Having a bit of a mystery here. I have long experience with using
subproject files, and have never seen this. I'm hoping someone can help.
I have a project file, created by others, which a Project Start date of
Feb 20. Per the Project Summary Task Bar, Start is 15 Feb (where the
actual first start of the earliest task is) and Finish is 27 Mar 2007
(which is when the last task finishes). This looks all ok.
When we insert this MPP file as a subproject into another empty file
(using the same standard calendar), the Project Summary Task finish date
remains the same (27 March 2007), but mysteriously the Project Summary
start date changes to May 3. Further, non of the tasks in the
subproject file shift right. They are shown to to the left of the start
of the Project Summary bar.
Clearly the Project Summary bar when inserted is wrong. But I can't
figure out what is wrong and why it recomputes this.
Thinking this a problem with Project 2003 SP2, I tried with Project 2002
SP-1, but get same result.
What causes the Project Summary Task bar to be wrong when inserted into
another file?