Hi Connie,
Thanks for the additional information.
I'm still not sure I follow (no fault of yours, just a hard time getting
my brain around your setup). What I think I understand is that you have
created a master project with inserted subprojects. The inserted
subprojects are embedded (linked) to the original project files. Then
what I think you are trying to do is to add some additional tasks to the
master project and then create information in the master which
summarizes the duration and work of different phases (Design, etc.) in
the subprojects. Good so far?
In quick testing I was able to recreate what I *think* you are seeing.
I created a new project file and inserted (through Insert > Project) 3
projects: Project A, Project B, and Project C. Each project contains
Design tasks and a summary Design task. So I have three summary tasks,
Project A Design, Project B Design, and Project C Design.
In the master project, I created a task (Master Design) and a milestone
Master Design complete. The Master Design task is task ID 1, the Master
Design complete milestone is task ID 2.
When I link Project A Design summary task as the predecessor to Master
Design milestone, a link line is drawn from Project A Design summary
task already in the project to the Master Design complete milestone.
The Master Design complete milestone is now task ID 3, but the "ghost"
task Project A Design summary does not appear above the Master Design
complete milestone.
I then link Project B Design summary as the predecessor to the Master
Design milestone. Again, a link line is drawn from Project B Design
summary to the milestone Master Design complete. Master Design complete
is now task ID 4.
I repeat the process, linking Project C Design summary as the
predecessor to the Master Design milestone. Again, link line is drawn,
the Master design milestone is now task ID 5, but the "ghost" task does
not appear.
If I remove Project A from the master project by selecting the inserted
project summary task and deleting, the Project A Design summary task now
appears as the "ghost" external predecessor.
I them remove Project B from the master project and Project B Design
summary task appears as the "ghost" external predecessor.
I remove Project C from the master and Project C Design summary tasks
appears.
I am now able to indent the three external predecessor tasks and the
Master Design complete milestone under the Master Design task. My task
list in the master is now:
ID 1 - Master Design summary task
ID 2 - Project A Design (external predecessor)
ID 3 - Project B Design (external predecessor)
ID 4 - Project C Design (external predecessor)
ID 5 - Master Design complete milestone
So, it is not until the inserted subprojects are removed that the
external predecessors appear as expected.
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.