Mark
I have a project where our calendar is set on a 5 day work week
(Monday-Friday). We plan to have a sub-contractor come in and pave on a
Saturday and when I try to assign the Saturday as a work day, the program
wants to set that Saturday as a workday for the entire project, affecting the
complete schedule.
How can I assign that Saturday as a workday for just one activity?