D
Duncan
I am getting twisted up on how to build a relatively simple plan. I think I
have reached the point where I am 2nd guessing myself too much as to what
impact changing task types, constraint types, etc. will have.
Task 1 is 2 hours of effort.
Task 2 is 4 hours of effort (dependency on Task 1).
Task 3 is 2 hours of effort (dependency on Task 2).
So I am estimating it taking 8 hours of effort to complete the above tasks.
The above tasks can occur any time between 9/15 and 9/26. They are sort of
a "do it in your spare time" type of tasks. I want to show that the work is
planned to occur during that two week window and I want to show how much of
an effot I feel it will take. That's on the plan the project side.
When I am recording the actual work on the plan, I would like to show what
date the work actually occured and how long it took, but that is not
absolutely critical.
I don't care about resources being overallocated, reports that show slipping
tasks, how effective plan vs actual was, etc. It is more of a "print out
the plan and show me where we are" type of project.
Thanks... I appreciate any help / suggestions.
have reached the point where I am 2nd guessing myself too much as to what
impact changing task types, constraint types, etc. will have.
Task 1 is 2 hours of effort.
Task 2 is 4 hours of effort (dependency on Task 1).
Task 3 is 2 hours of effort (dependency on Task 2).
So I am estimating it taking 8 hours of effort to complete the above tasks.
The above tasks can occur any time between 9/15 and 9/26. They are sort of
a "do it in your spare time" type of tasks. I want to show that the work is
planned to occur during that two week window and I want to show how much of
an effot I feel it will take. That's on the plan the project side.
When I am recording the actual work on the plan, I would like to show what
date the work actually occured and how long it took, but that is not
absolutely critical.
I don't care about resources being overallocated, reports that show slipping
tasks, how effective plan vs actual was, etc. It is more of a "print out
the plan and show me where we are" type of project.
Thanks... I appreciate any help / suggestions.