"Working times" for calendars incorrect

Joined
Mar 11, 2014
Messages
1
Reaction score
0
Hi. I am using Project 2013 Standard and have a very confusing problem.

If I click PROJECT->Change Working Time and look at the "Standard (Project Calendar)" entry I am correctly told it is a base calendar. However, the "Working times" entry for each working day is set to

08:00 to 12:00

i.e. there is no afternoon entry. If I look under the default entry for the working week I can see that each day has set

08:00 to 12:00
13:00 to 17:00

I have tried setting the correct times in each day explicitly (as may be seen in the attached screen shot) and using the project default, but each time I only see the half day shown. If I set a day to "non working time" then it is shown correctly as a non working time day.

Can anybody please help tell me what is going on?

Thanks

Dave
 

Attachments

  • Untitled.png
    Untitled.png
    43.6 KB · Views: 464

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top