S
Shannon D
I have two different calendars in MSP2007.
The 1st one aligns with Project/Options/Calendar of a 7.5 hrs day and 37.5
hr wk.
The 2nd calendars is a 8hr day and 40 hr wk.
I have set some of the tasks and resources with the 2nd calendar - however
when I assign 8hrs work it converts duration 1.07d even though these
resources/task should work an 8 hr day.
It it possible to have the above display 8hrs work and 1 d duration for one
type of resource/task and have another display 7.5 hrs work and 1 d duration
for a different type of resource/task?
The 1st one aligns with Project/Options/Calendar of a 7.5 hrs day and 37.5
hr wk.
The 2nd calendars is a 8hr day and 40 hr wk.
I have set some of the tasks and resources with the 2nd calendar - however
when I assign 8hrs work it converts duration 1.07d even though these
resources/task should work an 8 hr day.
It it possible to have the above display 8hrs work and 1 d duration for one
type of resource/task and have another display 7.5 hrs work and 1 d duration
for a different type of resource/task?