a task which starts when the earliest of several other tasks start

B

Benedykt

Hello,

in one project I have several tasks: machine 1, machine 2, machine 3
etc. They are in different summary tasks. Now I want to create a task
"machine's delivery", which must start when the earliest of those
"machine n" tasks start. The end date of this "machine's delivery"
task is not important for me. How can I achieve that?

Of course, I could collect all those "machine n" tasks in one summary
task and then the start date of this summary task would naturally be
the start day of those "machine n" tasks, but I don't want to do that
this way, because it would disintegrate my project's structure.

Does anybody have any idea?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top