Hello,
in one project I have several tasks: machine 1, machine 2, machine 3
etc. They are in different summary tasks. Now I want to create a task
"machine's delivery", which must start when the earliest of those
"machine n" tasks start. The end date of this "machine's delivery"
task is not important for me. How can I achieve that?
Of course, I could collect all those "machine n" tasks in one summary
task and then the start date of this summary task would naturally be
the start day of those "machine n" tasks, but I don't want to do that
this way, because it would disintegrate my project's structure.
Does anybody have any idea?
in one project I have several tasks: machine 1, machine 2, machine 3
etc. They are in different summary tasks. Now I want to create a task
"machine's delivery", which must start when the earliest of those
"machine n" tasks start. The end date of this "machine's delivery"
task is not important for me. How can I achieve that?
Of course, I could collect all those "machine n" tasks in one summary
task and then the start date of this summary task would naturally be
the start day of those "machine n" tasks, but I don't want to do that
this way, because it would disintegrate my project's structure.
Does anybody have any idea?