Actual Work being moved into the future for Project Professional 2

B

Barbara G

Hi,
I have a Fixed Work task in a project where the actual work moved from the
beginning of the year to the last part of 2009 and the early part of 2010.
Actual Work is protected through timesheets only in Project Server 2007. Do
you know why this time is being moved into the future? Do you know how I can
fix this?

Thanks,
 
M

Mike Glen

Hi Barbara,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top