M
Mohammed Barakat, PMP, MCTS, MCT
Greetings,
I’m facing a problem in assigning two of my resources in one of my projects,
and I would really appreciate your input to help me resolve it. The scenario
is as follows:
I have two Work resources:
John: available to work on the project only two hours a day.
Linda: available to work on the project only four hours a day.
I have a task (Task.A) that is expected to take 1 hour in duration.
I need to assign these two resources to the task. At the same time, I need
MS Project to show the overallocation for John if his total assignments in a
day exceed 2 hours, and show overallocation for Linda if her total
assignments in a day exceed 4 hours.
Questions:
1.What is the resource Max Limit in the resource sheet for each?
2.What is the Assignment Unit for each resource on Task.A?
3.What is the task type?
4.What is the Effort Driven status for Task.A?
5.Are there any options/adjustments to be done somewhere in the project plan
(like Tools/Options, Resource Calendars, etc.)
I use the Standard MS Project calendar.
Actually I tried many scenarios but either MS Project calculations are not
correct to me or overallocation was not reflected correctly.
Kind Regards,
Mohammed Barakat, PMP, MCTS, MCT
I’m facing a problem in assigning two of my resources in one of my projects,
and I would really appreciate your input to help me resolve it. The scenario
is as follows:
I have two Work resources:
John: available to work on the project only two hours a day.
Linda: available to work on the project only four hours a day.
I have a task (Task.A) that is expected to take 1 hour in duration.
I need to assign these two resources to the task. At the same time, I need
MS Project to show the overallocation for John if his total assignments in a
day exceed 2 hours, and show overallocation for Linda if her total
assignments in a day exceed 4 hours.
Questions:
1.What is the resource Max Limit in the resource sheet for each?
2.What is the Assignment Unit for each resource on Task.A?
3.What is the task type?
4.What is the Effort Driven status for Task.A?
5.Are there any options/adjustments to be done somewhere in the project plan
(like Tools/Options, Resource Calendars, etc.)
I use the Standard MS Project calendar.
Actually I tried many scenarios but either MS Project calculations are not
correct to me or overallocation was not reflected correctly.
Kind Regards,
Mohammed Barakat, PMP, MCTS, MCT