Thanks again for your suggestions,
Joseph Geretz
Hello Joseph,
When you make the initial (first) assignment of a resource to a
task, project calculates the work for the resource based upon
Duration * resource assignment units
If you set a 2 day duration task and assigned a resource at
100%, project will calculate 16 hours of work based upon the
above formula.
A method that works is to assign your 50% resource and enter 16
hours of work -- Project will then expand the duration of the
task to 4 days on the first pass. Using Resource Leveling in an
attempt to have project drop the assignment units to 50% will
not work -- the command will only delay tasks and will not
take action on a task where a resource is assigned at above
his/her maximum.
You may add the Work field to the task table (left side) and
enter the 16 hours of work and 2 days duration. Then when you
create your resource with a max. units of 50%, assign him/her
and project will recalculate the duration.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Joseph Geretz" wrote in message
Microsoft Project 2007
I have a task which I've estimated at 2 days worth of work. I
have a developer who is allocated roughly 50% of his time on
support issues. If I assign this developer to this task, I'd
expect the job to expand to 4 days after resource leveling is
performed. But that's not what happens at all. The task
duration remains fixed, as though the percentage allocation
was taken into account originally when the task duration was
entered.
From a management standpoint, this is decidedly unhelpful.
Indeed, at project estimation time, I often have no idea who
will actually be committed to the task, nor do I have any idea
what that person's available resources will be. What I need is
a way to define 'volume of work' ahead of time based on an
assumption of 100% resource allocation, and then have that
task duration recalculated based on the resource percentage
which is actually committed to that task.
Can Project 2007 accommodate this?
Thanks!
Joseph Geretz