A
Ammar Al-Saket
Hi Everyone,
What are overall recommendations (best practices) that planner needs to keep
in mind while developing a project schedule on MSP “beyond basic scheduling
issuesâ€. e.g. [critical path to look in certain way; total slack not to
exceed certain number; preference of use certain constrains or task types;
use of lag-lead in certain way; create buffer zone(s) …etc].
I do understand that each project is unique, and each project requires its
own arrangements, However, I also, think that there are some overall
scheduling selections that would lead to effective implementation of project.
Any contribution would be highly appreciated and thank you in advance…
_____
AS
What are overall recommendations (best practices) that planner needs to keep
in mind while developing a project schedule on MSP “beyond basic scheduling
issuesâ€. e.g. [critical path to look in certain way; total slack not to
exceed certain number; preference of use certain constrains or task types;
use of lag-lead in certain way; create buffer zone(s) …etc].
I do understand that each project is unique, and each project requires its
own arrangements, However, I also, think that there are some overall
scheduling selections that would lead to effective implementation of project.
Any contribution would be highly appreciated and thank you in advance…
_____
AS