Hi - I've just started working with MS Project and have a question.
Is it possible to "freeze" the top row project in the Gantt Chart view?
I have several projects (it will probably be more than twenty) that I need
to compare to a generic cycle that my department follows. This cycle is not a
summon of the other projects but totaly separate.
I have added this cycle as the first project in my file - but is it possible
to have it allways visible so that I can easily compare it to the projects at
the bottom of the file when i scroll down... Like the "freeze" faeture in
Excell.
Is it possible to "freeze" the top row project in the Gantt Chart view?
I have several projects (it will probably be more than twenty) that I need
to compare to a generic cycle that my department follows. This cycle is not a
summon of the other projects but totaly separate.
I have added this cycle as the first project in my file - but is it possible
to have it allways visible so that I can easily compare it to the projects at
the bottom of the file when i scroll down... Like the "freeze" faeture in
Excell.