You want to use baselines and earned value to get our "Planned Value". In
earned values terms this is called BCWS (Budgeted Cost of Work Scheduled).
Assign Costed Resources to detail tasks
set a baseline (Tools/Tracking/Set Baseline)
set the status date (Project/Project Information)
Now update your Remaining Work, Actual Work and Remaining Duration. This
will calculate your %Complete and %Work Complete.
To determine how many days you are in to a task, use a spare duration or
text column such as (Duration1) or (Text1). Right click on the field column
and choose Customize Fields. In the dialog that opens, you want to specify
"Formula" and then enter:
ProjDateDiff([Start],[Status Date])
This will give you the difference betweent the start date of the task and
the status date. However, there is some additional work to do (and I will
leave that as an ecercise for the poster....)
You will need to surround this formula in an If statement becuase you will
also want to exclude posting values when the start date is passed the status
date (future work) and then the task is already finished (Finish<Status Date).
If you look at my blog and browse the papers on Percent Complete, I give you
some formulas that you may be able to adapt to your purpose. Link is below.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
koolkat said:
Is there a column that you can insert that shows how many days into a task
you are? Also one for cost?
For example if I have a person at $500/day on a task for 10 days. Half way
through his task the cost will be $2500; is there a column that shows this?
I want to see daily the accumulitive cost.