J
JG
After I saved a baseline and ran the Gantt chart wizzard, the crtical
path does NOT display at all. I'm not sure if it's relevant or makes
any difference but for this project I chose the default task type
option to be 'fixed work'.
The only way I can 'force' a critical path to display is to the select
the 'calculate multiple critical paths' option checkbox.
Why do I have to make this selection to enable the cp to display? Is
there somthing I could check to see why I'm getting this unusual
behaviour?
Thanks!
Jonathan Glaser
(e-mail address removed)
path does NOT display at all. I'm not sure if it's relevant or makes
any difference but for this project I chose the default task type
option to be 'fixed work'.
The only way I can 'force' a critical path to display is to the select
the 'calculate multiple critical paths' option checkbox.
Why do I have to make this selection to enable the cp to display? Is
there somthing I could check to see why I'm getting this unusual
behaviour?
Thanks!
Jonathan Glaser
(e-mail address removed)