R
Riko Wichmann
Dear all,
I try to get the following report/summary/analysis out of MS Project -
either from Project itself or through an Excel export.
For the top level tasks (which are our so called work packages) I need
to see the planned investments (material resource), the personnel
costs (work resource * cost rate) and the total costs in time slices
(say quarters) over the full project life time. Investments and
personnel costs are calculated via custom fields using total cost and
work in hours.
So far, I managed to get either all the fields I want printed for all
top level tasks for the whole project life time (not sliced in
quarters) or just work and cost in quarter slices (but not the
customized fields I need).
I played with the reports, tables, views (both predefined and
customized) and the excel export without getting the desired results.
The excel export would mean to do all the calculations in excel which
is quite a lot of handy work since it's a big project. Since we are
still iterating the planning this is not really an acceptable
solution.
If anybody has any hints or ideas how to get this kind of table in an
automatic way, I would really appreciate it.
Thanks and Cheers,
Riko
I try to get the following report/summary/analysis out of MS Project -
either from Project itself or through an Excel export.
For the top level tasks (which are our so called work packages) I need
to see the planned investments (material resource), the personnel
costs (work resource * cost rate) and the total costs in time slices
(say quarters) over the full project life time. Investments and
personnel costs are calculated via custom fields using total cost and
work in hours.
So far, I managed to get either all the fields I want printed for all
top level tasks for the whole project life time (not sliced in
quarters) or just work and cost in quarter slices (but not the
customized fields I need).
I played with the reports, tables, views (both predefined and
customized) and the excel export without getting the desired results.
The excel export would mean to do all the calculations in excel which
is quite a lot of handy work since it's a big project. Since we are
still iterating the planning this is not really an acceptable
solution.
If anybody has any hints or ideas how to get this kind of table in an
automatic way, I would really appreciate it.
Thanks and Cheers,
Riko