S
Simon
Hello,
Is it possible to create custom timephased field in Project 2007
Server which would not be modified by standard project mechanisms?
My business case:
I need to track externally calculated actual costs in timephased field,
but in the same time I want to use standard planning features of MSP.
I need to avoid situation when changing task finish date, work/actual
work deletes data from the task timephased fields.
Is it possible to create custom timephased field in Project 2007
Server which would not be modified by standard project mechanisms?
My business case:
I need to track externally calculated actual costs in timephased field,
but in the same time I want to use standard planning features of MSP.
I need to avoid situation when changing task finish date, work/actual
work deletes data from the task timephased fields.