B
braden
I have a simple report that I want to run in a master project for al
sub projects, but can't figure out how.
I have a master project that currently has 7 sub-projects (and will hav
more in the future). All subproject tasks are exactly identical. I woul
like to have have a report with the subproject tasks down the left sid
(y-axis) and each sub-project title along the top (x-axis). Where tas
and sub-project title meet would simply be the percent complete the tas
is.
Is this possible to run and how so?
Thanks for all the help
sub projects, but can't figure out how.
I have a master project that currently has 7 sub-projects (and will hav
more in the future). All subproject tasks are exactly identical. I woul
like to have have a report with the subproject tasks down the left sid
(y-axis) and each sub-project title along the top (x-axis). Where tas
and sub-project title meet would simply be the percent complete the tas
is.
Is this possible to run and how so?
Thanks for all the help