N
NLC
Hi, I am trying to have the duration Column to calculate the actual number of
working days (not sure if it's the right term I'm using).
For example, I have a task summary named "Materials on Site", under this
task I have 2 indented tasks that each have duration of 1 day, 3 days apart
each other.
- Materials on Site
By default Project shows a duration of 5 days (10,11,12,13,14) for the task
summary, how do i set it to display the actual days required? (which is 2
days)
I hope this is clear, thanks a lot!
working days (not sure if it's the right term I'm using).
For example, I have a task summary named "Materials on Site", under this
task I have 2 indented tasks that each have duration of 1 day, 3 days apart
each other.
- Materials on Site
task 1 (08/Jun/10 - 08/Jun/10) duration 1 day
task 2 (08/Jun/14 - 08/Jun/14) duration 1 day
By default Project shows a duration of 5 days (10,11,12,13,14) for the task
summary, how do i set it to display the actual days required? (which is 2
days)
I hope this is clear, thanks a lot!