M
mjones
Hi All,
I hope someone knows how to do this ... and that it's possible.
If a person has a 4 hour task, but only two hours left in their sift,
I don't want them to do 2 hours of the task today and the remaining 2
hours the next day. I would like the task to wait until the next day
so it can be done all at once and not split across days.
Can this be done?
Thanks for any help you can give.
Michele
I hope someone knows how to do this ... and that it's possible.
If a person has a 4 hour task, but only two hours left in their sift,
I don't want them to do 2 hours of the task today and the remaining 2
hours the next day. I would like the task to wait until the next day
so it can be done all at once and not split across days.
Can this be done?
Thanks for any help you can give.
Michele