Carl Mankat
I am using MS Project 97. I am a bit rusty on some things. Right now I
have created a project using Duration to show the time in number of days
assigned to a task. I want to show the Work column and have it show the
number of hours assigned ie: Duration = 2 days, Work = 16 hrs. After
entering in my tasks I went back and inserted the Work column. However,
it is stuck on 0 hrs. no matter what the length of the task is. How do
I get the Work column to track the Duration in hors? I should know this
one but I'm missing something.
TIA,
Carl
have created a project using Duration to show the time in number of days
assigned to a task. I want to show the Work column and have it show the
number of hours assigned ie: Duration = 2 days, Work = 16 hrs. After
entering in my tasks I went back and inserted the Work column. However,
it is stuck on 0 hrs. no matter what the length of the task is. How do
I get the Work column to track the Duration in hors? I should know this
one but I'm missing something.
TIA,
Carl