N
Norman Goldsmith
MS Project 2002 SP-1, Windows XP
Project with two tasks, project starts on 2 February. Standard Gantt chart
displayed, entry table.
Task 1, duration 5 days, Start & End dates (copied & pasted in directly)
"February 2, 2009 8:00 AM" "February 6, 2009 5:00 PM", no calendar, sole
subtask of a summary that exactly repeats start, end and duration.
Task 2, duration 2 days (displayed), Start & End dates "February 7, 2009
8:00 AM" "February 8, 2009 5:00 PM", uses Weekend Calendar where only
Saturday and Sunday are workdays. Sole subtask of a summary that shows the
identical start and end dates but shows duration of 0 days!
Task 2 is linked FS to Task 1.
At the highest level another summary task, that has the two summary tasks as
subtasks. This task has start & end dates of "February 2, 2009 8:00 AM"
"February 8, 2009 5:00 PM". It has no assigned calendar and shows that the
duration is 5 days. Turning on the Project Summary task repeats the
information including the 5 day duration despite the span of 7 days.
On the Gantt chart side, all of the bars are of the correct length and
placement.
In the real project, tasks using the two calendars will be placed under a
single summary task. Is there a fix so that the duration field reports the
elapsed time correctly?
Thanks,
Project with two tasks, project starts on 2 February. Standard Gantt chart
displayed, entry table.
Task 1, duration 5 days, Start & End dates (copied & pasted in directly)
"February 2, 2009 8:00 AM" "February 6, 2009 5:00 PM", no calendar, sole
subtask of a summary that exactly repeats start, end and duration.
Task 2, duration 2 days (displayed), Start & End dates "February 7, 2009
8:00 AM" "February 8, 2009 5:00 PM", uses Weekend Calendar where only
Saturday and Sunday are workdays. Sole subtask of a summary that shows the
identical start and end dates but shows duration of 0 days!
Task 2 is linked FS to Task 1.
At the highest level another summary task, that has the two summary tasks as
subtasks. This task has start & end dates of "February 2, 2009 8:00 AM"
"February 8, 2009 5:00 PM". It has no assigned calendar and shows that the
duration is 5 days. Turning on the Project Summary task repeats the
information including the 5 day duration despite the span of 7 days.
On the Gantt chart side, all of the bars are of the correct length and
placement.
In the real project, tasks using the two calendars will be placed under a
single summary task. Is there a fix so that the duration field reports the
elapsed time correctly?
Thanks,