E
estysalinas
I have the following situation.
Resources work hours allow for:
R1- 45 hour/week
R2- 45 hour/week
R3- 40 hour/week
*45 is the base cal, 40 is a work week override.
Task 1 is assigned to R1 for 90 hours, Task 2 is assigned to R2 for 90
hours, Task 3 is assigned to R3 for 90 hours.
All the tasks show a duration of 10 days. The start and end dates show 10
days for Task 1 and 2, however for task 3, it shows an end date of +1 day of
the other tasks resources. This makes sense because he is on a 40 hour
workweek.
Why does project keep the duration of Taks 3 @ 10 days when the work time is
really 11 days, and start and finish days show 11 days. The task is actually
taking 11 days to complete and not 10 days. Am i missing something? Thanks!
Resources work hours allow for:
R1- 45 hour/week
R2- 45 hour/week
R3- 40 hour/week
*45 is the base cal, 40 is a work week override.
Task 1 is assigned to R1 for 90 hours, Task 2 is assigned to R2 for 90
hours, Task 3 is assigned to R3 for 90 hours.
All the tasks show a duration of 10 days. The start and end dates show 10
days for Task 1 and 2, however for task 3, it shows an end date of +1 day of
the other tasks resources. This makes sense because he is on a 40 hour
workweek.
Why does project keep the duration of Taks 3 @ 10 days when the work time is
really 11 days, and start and finish days show 11 days. The task is actually
taking 11 days to complete and not 10 days. Am i missing something? Thanks!