D
Dann
I need to do some "what if" analysis on my plan. The plan is well designed
for CP, that is everything is linked, no summary tasks are linked, etc. Right
now, the project is about two-week's behind where we would like it to be. I
can identify the tasks that are driving the schedule...because they are on
the critical path. (Imagine that!) I also know that one of the larger tasks,
application development, is currently driving change from week-to-week status
updates. But, cutting development by two weeks will not "automatically" bring
the end date in two weeks.
My question this: What is the most efficient way to determine what will be
on the critical path if I remove the current constraint, the development
time. Of course, I could make changes to the plan to see what happens, but
I'm hoping there is a more structured approach. I've also looked at Total
Slack, thinking that will tell me which tasks are likely to end up on the
critical path if the development time shortens. Is that a valid assumption on
my part? Is there some other way to determine what will go critical if
current critical tasks are shortened?
for CP, that is everything is linked, no summary tasks are linked, etc. Right
now, the project is about two-week's behind where we would like it to be. I
can identify the tasks that are driving the schedule...because they are on
the critical path. (Imagine that!) I also know that one of the larger tasks,
application development, is currently driving change from week-to-week status
updates. But, cutting development by two weeks will not "automatically" bring
the end date in two weeks.
My question this: What is the most efficient way to determine what will be
on the critical path if I remove the current constraint, the development
time. Of course, I could make changes to the plan to see what happens, but
I'm hoping there is a more structured approach. I've also looked at Total
Slack, thinking that will tell me which tasks are likely to end up on the
critical path if the development time shortens. Is that a valid assumption on
my part? Is there some other way to determine what will go critical if
current critical tasks are shortened?