R
Robin Roe
Hi,
We would like to enter actual information onto the schedule, but when I
change Actual Work it affects Actual Duration and visa versa.
Example.
A Task with a 5 day duration and a Resource assigned 40hrs (100%)
When updating I assign an Actual Start and Actual Finish date (which in this
case is as planned i.e. 5 day duration). Project marks the task as 100%
complete and the Actual Work is filled out as 40hrs, 100% complete, as I
would expect. I now try to amend the actual work back to 32 hrs and project
recalculates the remaining as 8hrs. When I try zeroing the Remaining Work
field, the Actual Duration (which I had already told it was 5 days) now
changes to 4 days. I understand why this is happening, but it doesn’t really
follow reality. Basically what I want is for Actual Duration and Actual Work
to be independent of each other. I have tried using “Updating task status
updates resource status†setting, but this doesn’t seem to work when the
project is set as 100% (from my first step above). Reading other post the
only possible way around this is to update the resource time sheet (right
hand pane of task usage view)
Any help would be much appreciated.
Thanks
We would like to enter actual information onto the schedule, but when I
change Actual Work it affects Actual Duration and visa versa.
Example.
A Task with a 5 day duration and a Resource assigned 40hrs (100%)
When updating I assign an Actual Start and Actual Finish date (which in this
case is as planned i.e. 5 day duration). Project marks the task as 100%
complete and the Actual Work is filled out as 40hrs, 100% complete, as I
would expect. I now try to amend the actual work back to 32 hrs and project
recalculates the remaining as 8hrs. When I try zeroing the Remaining Work
field, the Actual Duration (which I had already told it was 5 days) now
changes to 4 days. I understand why this is happening, but it doesn’t really
follow reality. Basically what I want is for Actual Duration and Actual Work
to be independent of each other. I have tried using “Updating task status
updates resource status†setting, but this doesn’t seem to work when the
project is set as 100% (from my first step above). Reading other post the
only possible way around this is to update the resource time sheet (right
hand pane of task usage view)
Any help would be much appreciated.
Thanks