Hi,
I have a enterprise resource that has 100% max units (total availability
across all projects). There are two projects where that resource should only
be available 50% of the time to each project. The only way I have been able
to do this is to set the resource assignment to 50% for each task in both
projects. Is there an easier way to set a enterprise resource's availability
for a single project?
Thanks,
Kiley Hykawy
Senior Software Developer
Tantia Technologies Canada Inc.