Hi,
Can I exclude a resource from leveling in my project schedule? The only
thing I've come up with is to create a cost resource with zero cost and
assign it to the task. It is a zero cost resource for me as the work is
being done by another trade so I need to manually enter the start/end and
updates for this task so my dependent tasks stay on track. I need this as
resource because some tasks are done jointly with us and them. Just want to
know if there is a better way to handle this. Thanks.
Regards-Michael G.
Can I exclude a resource from leveling in my project schedule? The only
thing I've come up with is to create a cost resource with zero cost and
assign it to the task. It is a zero cost resource for me as the work is
being done by another trade so I need to manually enter the start/end and
updates for this task so my dependent tasks stay on track. I need this as
resource because some tasks are done jointly with us and them. Just want to
know if there is a better way to handle this. Thanks.
Regards-Michael G.