D
datatape
Hi all,
The consideration is that, using Project 2003 Server, I suffered a huge
increase of insertion in the SQL database (the proportion is more than 1 to
100) because of the selection of the "Expand timephased data in the database"
option in published projects containing assignments. Said increase has
determined an unacceptable decrease in performances (lengthy project savings).
The issue anyway is: I wish to import actual data (actual work) from an
external system (HR system) in the EPM system. Is there an optimal
method/tool? Are expanded timephased data in the EPM database necessary to
reach such goal?
Any consideration will be helpful.
Angelo
The consideration is that, using Project 2003 Server, I suffered a huge
increase of insertion in the SQL database (the proportion is more than 1 to
100) because of the selection of the "Expand timephased data in the database"
option in published projects containing assignments. Said increase has
determined an unacceptable decrease in performances (lengthy project savings).
The issue anyway is: I wish to import actual data (actual work) from an
external system (HR system) in the EPM system. Is there an optimal
method/tool? Are expanded timephased data in the EPM database necessary to
reach such goal?
Any consideration will be helpful.
Angelo