Hi,
I've flagged several summary tasks. I'm trying to find/create a filter that
will show only the flagged summary tasks and all related subtasks that are <
100% complete. If a filter won't solve my problem, can a formula solve? Thank
you.
Robert
I've flagged several summary tasks. I'm trying to find/create a filter that
will show only the flagged summary tasks and all related subtasks that are <
100% complete. If a filter won't solve my problem, can a formula solve? Thank
you.
Robert