C
Catfish Hunter
How can I make the Finish Variance calculate off of Baseline 1?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
Catfish Hunter said:How can I make the Finish Variance calculate off of Baseline 1?
Catfish Hunter said:Thanks for your assistance.
Is there a way to copy the Baseline 1 to Baseline. This would be my
preferance to show finish variance over your suggestion. The project is about
1,300 task. I thought of doing a cut and paste from Baseline 1 start/finish
to Baseline start/finish. Is there another way?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
Catfish Hunter said:How can I make the Finish Variance calculate off of Baseline 1?
Catfish Hunter said:Thanks for your assistance.
Is there a way to copy the Baseline 1 to Baseline. This would be my
preferance to show finish variance over your suggestion. The project is
about
1,300 task. I thought of doing a cut and paste from Baseline 1
start/finish
to Baseline start/finish. Is there another way?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the
following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
message
How can I make the Finish Variance calculate off of Baseline 1?
John said:Catfish Hunter said:Thanks for your assistance.
Is there a way to copy the Baseline 1 to Baseline. This would be my
preferance to show finish variance over your suggestion. The project is
about
1,300 task. I thought of doing a cut and paste from Baseline 1
start/finish
to Baseline start/finish. Is there another way?
Catfish,
There are a couple other ways I can think of but I wouldn't say they are
necessarily any better than cut and paste. The first is to drag and
drop. Select all of Baseline1 Start and Finish and drag it to Baseline
Start and Finish respectively. The second method is to use VBA but even
in my pro-VBA opinion, that's way overkill.
John
Project MVPDale Howard said:Catfish --
You would need to use a custom task Duration field containing the
following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
message
How can I make the Finish Variance calculate off of Baseline 1?
John --
There's a very simple way to do this, and to preserver the original Baseline
values in the process. See my answer to Catfish's question.
Catfish Hunter said:Thanks for your assistance.
Is there a way to copy the Baseline 1 to Baseline. This would be my
preferance to show finish variance over your suggestion. The project is
about
1,300 task. I thought of doing a cut and paste from Baseline 1
start/finish
to Baseline start/finish. Is there another way?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the
following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
message
How can I make the Finish Variance calculate off of Baseline 1?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
Catfish Hunter said:How can I make the Finish Variance calculate off of Baseline 1?
Melissa said:Hi Dale,
can you please walk me through the steps to create this custom field?
Thanks!
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
How can I make the Finish Variance calculate off of Baseline 1?
Jan De Messemaeker said:Tools
Customize
Fields
Select Duration1 (for instance)
Select Formula
Enter the formula
OK
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Melissa said:Hi Dale,
can you please walk me through the steps to create this custom field?
Thanks!
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
How can I make the Finish Variance calculate off of Baseline 1?
Thanks, Jan!
That's exactly what I did before I posted the message but I was
afraid I will be wiping out an original formula because I was
prompted with message that existing data for Duration 1 will be
deleted.
How can I check what the original formula is and whether any of my
data will be affected by the change?
Jan De Messemaeker said:Tools
Customize
Fields
Select Duration1 (for instance)
Select Formula
Enter the formula
OK
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Melissa said:Hi Dale,
can you please walk me through the steps to create this custom
field? Thanks!
:
Catfish --
You would need to use a custom task Duration field containing the
following formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
in message
How can I make the Finish Variance calculate off of Baseline 1?
Mike Glen said:Hi Melissa,
Right-click on the column header and select Customize Fields... and in the
dialog, click the Formula... button. Examine the white space - all white
means no formula. If there is a furmula, it will be listed here.
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Thanks, Jan!
That's exactly what I did before I posted the message but I was
afraid I will be wiping out an original formula because I was
prompted with message that existing data for Duration 1 will be
deleted.
How can I check what the original formula is and whether any of my
data will be affected by the change?
Jan De Messemaeker said:Tools
Customize
Fields
Select Duration1 (for instance)
Select Formula
Enter the formula
OK
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Melissa" <[email protected]> schreef in bericht
Hi Dale,
can you please walk me through the steps to create this custom
field? Thanks!
:
Catfish --
You would need to use a custom task Duration field containing the
following formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
in message
How can I make the Finish Variance calculate off of Baseline 1?
Yup, there was no formula when I first clicked on "Formula" so I'll
proceed with the customisation. Thanks for all your help!
Mike Glen said:Hi Melissa,
Right-click on the column header and select Customize Fields... and
in the dialog, click the Formula... button. Examine the white space
- all white means no formula. If there is a furmula, it will be
listed here.
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
Thanks, Jan!
That's exactly what I did before I posted the message but I was
afraid I will be wiping out an original formula because I was
prompted with message that existing data for Duration 1 will be
deleted.
How can I check what the original formula is and whether any of my
data will be affected by the change?
:
Tools
Customize
Fields
Select Duration1 (for instance)
Select Formula
Enter the formula
OK
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Melissa" <[email protected]> schreef in bericht
Hi Dale,
can you please walk me through the steps to create this custom
field? Thanks!
:
Catfish --
You would need to use a custom task Duration field containing the
following formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
in message
How can I make the Finish Variance calculate off of Baseline 1?
Dale Howard said:Catfish --
You would need to use a custom task Duration field containing the following
formula:
[Finish] - [Baseline1 Finish]
Hope this helps.
Catfish Hunter said:How can I make the Finish Variance calculate off of Baseline 1?
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.