H
Heidi
Hi,
I have a project plan with internal resources and external resources
(offsite teams) assigned to tasks. The internal resources have hours
in the project and offsite teams do not have hours. (They are paid by
deliverables regardless of hours.)
Because I do not want the external hours worked to calculate into the
total hours of work on the project, I am using fixed duration without
effort driven checked. When I assign the external resource I clear
the units and work to zero. This worked great in previous versions of
Project.
When I upgraded to Project 2007 and opened my plan all the tasks (both
complete and incomplete) with only the external resources assigned
were changed to zero duration. (Yikes!)
I tried adding a new row, in case the task was corrupted, but this
behavior seems to be by design. (??)
When I try to re-key the duration onto a task, Project immediately
makes the task zero duration again. I can remove the resource and
get the duration to stick, but once I add the resource and zero the
units, the duration goes to zero again.
Why can't I get my tasks to have a FIXED Duration, regardless of
resource assignment? If not, do you know of any work around that
allows me to assign a resource to a task without hours?
Thanks for any help you can provide,
Heidi
I have a project plan with internal resources and external resources
(offsite teams) assigned to tasks. The internal resources have hours
in the project and offsite teams do not have hours. (They are paid by
deliverables regardless of hours.)
Because I do not want the external hours worked to calculate into the
total hours of work on the project, I am using fixed duration without
effort driven checked. When I assign the external resource I clear
the units and work to zero. This worked great in previous versions of
Project.
When I upgraded to Project 2007 and opened my plan all the tasks (both
complete and incomplete) with only the external resources assigned
were changed to zero duration. (Yikes!)
I tried adding a new row, in case the task was corrupted, but this
behavior seems to be by design. (??)
When I try to re-key the duration onto a task, Project immediately
makes the task zero duration again. I can remove the resource and
get the duration to stick, but once I add the resource and zero the
units, the duration goes to zero again.
Why can't I get my tasks to have a FIXED Duration, regardless of
resource assignment? If not, do you know of any work around that
allows me to assign a resource to a task without hours?
Thanks for any help you can provide,
Heidi