T
TJ
Hi
The project I am planning has a task (or role) which is performed by a
single resource, is fixed at a number of days, and can happen at any
or different points of the project. An example is an auditor will
spend 5 days over the life of the project reviewing the project
progression.
In the Microsoft Project I would like to represent this in the
following way:
- In the Gantt a single bar stretches from the beginning to the end.
It has no linking tasks.
- The Start date is based on the first task of the project. Can this
be dynamic, based on the start date of the first task?
- The Finish date is based on the last task of the project. Can this
be dynamic, based on the finish date of the last task?
- The duration is to be locked at 5 days. Can the Resource Units
percent be adjusted automatically depending on the Start date and
Finish date?
I am a newbie to MS Project. If anybody knows how to do this I would
be most appreciated.
Thanks,
TJ
The project I am planning has a task (or role) which is performed by a
single resource, is fixed at a number of days, and can happen at any
or different points of the project. An example is an auditor will
spend 5 days over the life of the project reviewing the project
progression.
In the Microsoft Project I would like to represent this in the
following way:
- In the Gantt a single bar stretches from the beginning to the end.
It has no linking tasks.
- The Start date is based on the first task of the project. Can this
be dynamic, based on the start date of the first task?
- The Finish date is based on the last task of the project. Can this
be dynamic, based on the finish date of the last task?
- The duration is to be locked at 5 days. Can the Resource Units
percent be adjusted automatically depending on the Start date and
Finish date?
I am a newbie to MS Project. If anybody knows how to do this I would
be most appreciated.
Thanks,
TJ