If you double click on the task name, in the dialog box
that comes up you will see a Start and Finish date for
the task under the General tab.

Hope this gives you what you need.

John Cello
John Cello Consulting
Communications For Business
www.johncelloconsulting.com
-----Original Message-----
Hi, I'm reasonably new to MSP, and have a need to fix
the Start AND End date of a task. Is there a way of doing
this? All the available constraints seem to apply to
either one or the other....
 