How do I check resource pool working time exceptions?

J

jas431

I have a resource pool that is used across several project plans and thus
updated by several different project managers.
Is there any easy way of finding out the working time exceptions for each
member of the resource pool?
Currently I have to look at the calender for each resource.
A report or view where I can see all working exceptions would be great.

I'm trying to check that everyone's holidays have been entered correctly.
 
J

Jonathan Sofer [MVP]

While you have the resource pool open, you can run a report from
Report>Reports... (if using Pro 2007) or View>Reports (if using Pro 2003)

Select Custom
Select Resource, click Edit
Navigate to Details tab and check the Resource>Calendar checkbox and uncheck
anything else that might be checked.
Click OK
Clikc Preview
 
C

C

Hi Jas,

I use the same method. I set the standard calendar to reflect the company
holidays and applied this to all resources. To modify an individual resource
I would go to that specific resource's calendar and set their
timeoff/vacations. This way everyone has the same standard Holidays.

Cheers!

Cheryl
 