Robert Mitchell
My company is a homebuilding company and we are attempting to create a
schedule for all project start up activities. At a high level, the tasks
required are the same (e.g., Develop Land, Determine Product Mix, Apply for
and Obtain Building Permits, etc.) However, below that level, each project is
a unique set of tasks. I would like to be able to accomplish the following,
if possible?
Allow department managers to schedule and assign tasks without being
Microsoft Project experts. Can department managers add duration through
Project Central?
Assign tasks to resources without defining the amount of work to be done. We
want to notify resources of their assignment and the begin and end date, but
not load resources on the plan. Does Project Central allow for messaging
without a number of hours of work being assigned? In essence, we want to use
Project Central to distribute project assignments, but not track hours
worked.
Allow resources to modify the projected start and end dates. Can a resource
in Project Central modify the actual start and end dates (in the future) and
change the projected start and end dates?
Sorry that these questions are somewhat vaque. We are a one man IT shop and
I don't have the resources to fully train department managers on Microsoft
Project. I am hoping to use Project Central to distribute, collect and
publish the information required.
schedule for all project start up activities. At a high level, the tasks
required are the same (e.g., Develop Land, Determine Product Mix, Apply for
and Obtain Building Permits, etc.) However, below that level, each project is
a unique set of tasks. I would like to be able to accomplish the following,
if possible?
Allow department managers to schedule and assign tasks without being
Microsoft Project experts. Can department managers add duration through
Project Central?
Assign tasks to resources without defining the amount of work to be done. We
want to notify resources of their assignment and the begin and end date, but
not load resources on the plan. Does Project Central allow for messaging
without a number of hours of work being assigned? In essence, we want to use
Project Central to distribute project assignments, but not track hours
worked.
Allow resources to modify the projected start and end dates. Can a resource
in Project Central modify the actual start and end dates (in the future) and
change the projected start and end dates?
Sorry that these questions are somewhat vaque. We are a one man IT shop and
I don't have the resources to fully train department managers on Microsoft
Project. I am hoping to use Project Central to distribute, collect and
publish the information required.