K
KENTSTER
I've always been taught and have made an effort to assure every activity in
my project has both front end and back logic ties. The first activity in the
project does not have a predecesor and the last activity has no successor.
All other have both. In Project, I have not find an easy, simple way to
identify activities that, for whatever reason, did not get logic ties. Is
there an analysis report I can run that will display all activities with open
ends?
Thanks
my project has both front end and back logic ties. The first activity in the
project does not have a predecesor and the last activity has no successor.
All other have both. In Project, I have not find an easy, simple way to
identify activities that, for whatever reason, did not get logic ties. Is
there an analysis report I can run that will display all activities with open
ends?
Thanks