T
turtle
When i import my start and finish dates into project is changes the
finish dates based on the duration of the task. I want it to keep my
finish dates rather than computing.
For an example i might have 20 hours of work between Jan and Mar so i
want it to default to 1/1/08 and 3/31/08 for the start and finish. It
wants to put in 1/1/08 and 1/3/08 (20hrs = 3 days).
any help would be great!
thanks,
KO
finish dates based on the duration of the task. I want it to keep my
finish dates rather than computing.
For an example i might have 20 hours of work between Jan and Mar so i
want it to default to 1/1/08 and 3/31/08 for the start and finish. It
wants to put in 1/1/08 and 1/3/08 (20hrs = 3 days).
any help would be great!
thanks,
KO