R
rewb2
We recently got Project 2007 at my work, in order to generate GANTT
charts. At the moment we are very unsophisticated users, and all we
are intending to do is to represent graphically a timeline of a
project, showing what is occurring on which days over a two month
period.
We have not attempted to include any resource details, and hence have
not assigned the tasks in any way. All the 'project' thinking is done
outside of the software (i.e. we effectively know exactly what tasks
we want to do when). Where we use dependencies, this is simply to
represent that a certain task cannot start until another one has
finished, but if our 'plan' is for the second task to start on a
certain date, that is the date that we will have the second task start
(even if this is two weeks after the end of the first task). We
understand that we are not using any of the Project functionality, and
are effectively 'hard-coding' / forcing Project to do what we want.
I've seen comments suggesting that Project is not the tool for
somebody who wants to do the above (e.g. why not just use Excel?), but
having a standard-format GANTT-style chart as an output is something
that we want. Would be interesting in hearing people's thoughts on
this. Most of the work we're doing in Project now is wrestling with
various calendar issues etc (as far as we're concerned, a day is a
discrete 24-hour amount of time, which is either active for a certain
task, or is not - we don't want 8 hour working days, weekends as non-
working time, or anything like that).
charts. At the moment we are very unsophisticated users, and all we
are intending to do is to represent graphically a timeline of a
project, showing what is occurring on which days over a two month
period.
We have not attempted to include any resource details, and hence have
not assigned the tasks in any way. All the 'project' thinking is done
outside of the software (i.e. we effectively know exactly what tasks
we want to do when). Where we use dependencies, this is simply to
represent that a certain task cannot start until another one has
finished, but if our 'plan' is for the second task to start on a
certain date, that is the date that we will have the second task start
(even if this is two weeks after the end of the first task). We
understand that we are not using any of the Project functionality, and
are effectively 'hard-coding' / forcing Project to do what we want.
I've seen comments suggesting that Project is not the tool for
somebody who wants to do the above (e.g. why not just use Excel?), but
having a standard-format GANTT-style chart as an output is something
that we want. Would be interesting in hearing people's thoughts on
this. Most of the work we're doing in Project now is wrestling with
various calendar issues etc (as far as we're concerned, a day is a
discrete 24-hour amount of time, which is either active for a certain
task, or is not - we don't want 8 hour working days, weekends as non-
working time, or anything like that).