K
ks2008
Is there any difference between the Task Calendar, Project Calendar and
Resource Calendar other that where it is applied.
Meaning
*Resource Calendar: *Calendar Applied against the Resource.
*Task Calendar : *Calendar Applied against the Task.
*Project Calendar: * Calendar Applied against the entire project.
All three type of calendars are created using the same steps and the
scope of all three calendar are the same, that is to entire project.
Is my understanding is correct ?
Resource Calendar other that where it is applied.
Meaning
*Resource Calendar: *Calendar Applied against the Resource.
*Task Calendar : *Calendar Applied against the Task.
*Project Calendar: * Calendar Applied against the entire project.
All three type of calendars are created using the same steps and the
scope of all three calendar are the same, that is to entire project.
Is my understanding is correct ?