Using Project Pro 2003, SP3
I have FS, SS, & FF links between various tasks.
For example, I have FS links between tasks A-B-C-D.
When I change the start date for A, the dates for B-C-D should be
updated accordingly. However, that is not the case. When I change
the date for A, A moves but there is not movement for B-C-D. I
observe the same behavior with the other links. There are no
constraints on these tasks.
I have checked the options and cannot find anything that would cause
this.
Anybody know what is going on here?
meg99
I have FS, SS, & FF links between various tasks.
For example, I have FS links between tasks A-B-C-D.
When I change the start date for A, the dates for B-C-D should be
updated accordingly. However, that is not the case. When I change
the date for A, A moves but there is not movement for B-C-D. I
observe the same behavior with the other links. There are no
constraints on these tasks.
I have checked the options and cannot find anything that would cause
this.
Anybody know what is going on here?
meg99