Max units in Resource Pool vs. Sharer Files

B

Bobg

Hello,
I am setting up some projects to share resources from a resource pool. My
original plan was to have the max units set at 90% in the Resource Pool
(allowing resources to spend 90% of their time on projects in general), and
then to set the max units lower in the sharer files, if necessary. This was
done so that scheduling for an individual project could be controlled by how
much time was allocated to each project, but the resource pool would not show
over allocations unless someone was above the 90% threshold. I set the
conflict option to Sharer takes precedence.

I have two observations:

1. For my first project, I set the max units to 50% within the project. This
appeared to work but when I reopened the project, only resources that had
been assigned to tasks retained the 50%, the remaining resources defaulted
back to the 90% max units from the resource pool.

2. When I introduced an additional project, and wanted to set max units at
25%, it became more confusing... the first project changed to the 25% defined
in the second project.

So my question is - is there a way to do what I am describing at the max
units level, or is there a better way to do this?

Thank you in advance for any suggestions!

Bob
 
R

Rod Gill

Once you share a resource pool there can only be one... max units!

For projects where 50% is the availability allowed the PM will need to know
they can only use 20h/week and level their resource workload to this level.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top