Migrated projects' baselines are not calculating

J

JoB1

We just migrated our PS 2003 environment to PS 2007 SP1.
Now that we are safely on the other side of the migration, I have noticed an
issue with migrated projects.
In the Views (like Resource Usage), baseline work and cost don’t display
summary (rollup) info
New projects with new baselines (post migration) seem to work fine.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question