K
KC
The following two questions, with answer key and explanations, were on a
recent quiz over MS Project and assigning resources. I have queried the
author(s) of this quiz, who are supposedly are qualified project
consultants, but have yet to get any explanation as to the validity of their
statements/correct answers. Here are the questions with the answer keys:
1. If you have 400% allocated for Builder, what ways can this be represented
in Microsoft Project using a weekly duration? For this question, you will
choose more than one option for your answer.
4 resources at 100% for 1 week CORRECT ANSWER
2 resources at 100% for 4 weeks
1 resource at 100% for 2 weeks
8 resources at 50% for 1 week CORRECT ANSWER
1 resource at 100% for 4 weeks CORRECT ANSWER
Instructor Explanation : In project, the allocation % is the total available
allocation based on the calendar week settings in Microsoft project. So, in
typical default Microsoft Project Settings, there is a 40h week, so 100%
allocation of 1 resource is 40h. If you have 4 resources, then it is 400%.
2. Select the exact resources hour allocation available to the ACME
Construction project based on the resource allocation percentage. For this
question, you will choose more than one option for your answer. HINT: from
the Resource Sheet, take the Max. Units and multiply this by 40 hours.
Points:
Architect - 120 CORRECT ANSWER (Note: Max units is 300%)
Engineer - 250
Electrician - 100
Builder - 80 CORRECT ANSWER (Note: Max units is 200%)
Landscaper - 240 CORRECT ANSWER (Note: Max units is 600%)
Purchasing - 20
Instructor Explanation : In project, the allocation % is the total available
allocation based on the calendar week settings in Microsoft project. So, in
typical default Microsoft Project Settings, there is a 40h week, so 100%
allocation of 1 resource is 40h. If you have 4 resources, then it is 400%.
Any comments? or are both questions answered correctly and explanations
accurate?
recent quiz over MS Project and assigning resources. I have queried the
author(s) of this quiz, who are supposedly are qualified project
consultants, but have yet to get any explanation as to the validity of their
statements/correct answers. Here are the questions with the answer keys:
1. If you have 400% allocated for Builder, what ways can this be represented
in Microsoft Project using a weekly duration? For this question, you will
choose more than one option for your answer.
4 resources at 100% for 1 week CORRECT ANSWER
2 resources at 100% for 4 weeks
1 resource at 100% for 2 weeks
8 resources at 50% for 1 week CORRECT ANSWER
1 resource at 100% for 4 weeks CORRECT ANSWER
Instructor Explanation : In project, the allocation % is the total available
allocation based on the calendar week settings in Microsoft project. So, in
typical default Microsoft Project Settings, there is a 40h week, so 100%
allocation of 1 resource is 40h. If you have 4 resources, then it is 400%.
2. Select the exact resources hour allocation available to the ACME
Construction project based on the resource allocation percentage. For this
question, you will choose more than one option for your answer. HINT: from
the Resource Sheet, take the Max. Units and multiply this by 40 hours.
Points:
Architect - 120 CORRECT ANSWER (Note: Max units is 300%)
Engineer - 250
Electrician - 100
Builder - 80 CORRECT ANSWER (Note: Max units is 200%)
Landscaper - 240 CORRECT ANSWER (Note: Max units is 600%)
Purchasing - 20
Instructor Explanation : In project, the allocation % is the total available
allocation based on the calendar week settings in Microsoft project. So, in
typical default Microsoft Project Settings, there is a 40h week, so 100%
allocation of 1 resource is 40h. If you have 4 resources, then it is 400%.
Any comments? or are both questions answered correctly and explanations
accurate?